Sprint | Tasks Description |
---|---|
Sprint 1 | Sprint Planning Meeting |
Personas Specification | |
Scenarios Specification | |
Extraction of Requirements from the Personas and Scenarios | |
Development of Use-Case Diagrams | |
Use Case Prioritization | |
Retrospective Meeting between the Analysis and Design Team and Management Team on Lessons Learned | |
Sprint 2 Sprint 3 Sprint 4 Sprint 5 | Sprint Planning Meeting |
Interaction Modeling for Use Cases: A (Sprint 2), B (Sprint 3), C (Sprint 4) and D (Sprint 5) | |
Use Case Specifications: A (Sprint 2), B (Sprint 3), C (Sprint 4) and D (Sprint 4) | |
Development of Prototypes for Use Cases: A (Sprint 2), B (Sprint 3), C (Sprint 4) and D (Sprint 5) | |
Development of Activity Diagrams for Use Cases: A (Sprint 2), B (Sprint 3), C (Sprint 4) and D (Sprint 5) | |
Retrospective Meeting between the Analysis and Design Team and the Management Team on Lessons Learned | |
Sprint 6 | Sprint Planning Meeting |
Improvements in the Artifacts of the Previous Sprints | |
Retrospective Meeting between the Analysis and Design Team and the Management Team on Lessons Learned |